Plan of Creating Infrastructure Facilities
All objects on the Investment Map of Kaluga Region (section "Information layers")
Vorsino Industrial Park:
- Construction of facility: Stormwater drain system for enterprises located at Eastern Site-1 of Vorsino Industrial Park. 2nd construction phase
- Construction of facility: Distribution high-pressure gas pipeline for Vorsino Industrial Park OOO. Eastern Site-1, Kaluga Region, Borovsk District. Stage 7, 2nd construction phase
- Construction of facility: Novamedika Pharmaceutical Plant for manufacturing sterile pharmaceuticals in Kaluga Region. 10 kV power grid
- Construction of facility: 10 kV power grid, II reliability class for industrial enterprises of Vorsino Industrial Park, 5MW maximum capacity. 2nd construction phase
- Construction of facility: 10kV Power Distribution Station RP-10-UKHL1 with 10MW maximum capacity cable lines, II reliability class for Gabriel-Chemie-Rus-2 OOO, ELA Container RU OOO and for future industrial enterprises at Eastern Site-2 of Vorsino Industrial Park
- Design and construction of power grid to tie-in point of Part Inn OOO facility
- Design and construction of power grid to tie-in point of B-Pharm OOO investment facility
- Design and construction of facility: Stormwater drain system for Gabriel-Chemie-Rus-2 OOO, ELA Container RU OOO and for future industrial enterprises at Eastern Site-2 of Vorsino Industrial Park
- Preparation of planning project and boundary-setting plan for Vorsino Industrial Park
- Design and construction of facility: Relocation of utilities (water supply, water disposal, Stormwater drain system) at the Western site of Vorsino Industrial Park in the area of Total Vostok enterprise
- Construction of facility: Parking complex for heavy trucks at the territory of the Western site of Vorsino Industrial Park. Phase I
- Design of facility: Modernization of motor roads with organization of public transport traffic at the Western site of Vorsino Industrial Park
- Construction of facility: Modernization of motor roads with organization of public transport traffic at the Western site of Vorsino Industrial Park
- Front-end engineering and design: Activities to ensure continuous operation of distribution network of water supply at the Western site of Vorsino Industrial Park
- Design and construction of facility: Pump station, 3rd rise level, Western site of Vorsino Industrial Park
- Design of facility: Regulating pond for stormwater drainage surface run-off at the Western site of Vorsino Industrial Park
- Construction of facility: Regulating pond for stormwater drainage surface run-off at the Western site of Vorsino Industrial Park
Grabtsevo Industrial Park:
- Design and construction of facility: Complementary parking for 200 parking slots (pursuant to cooperation agreement with Volkswagen Group Rus OOO, Engine Plant, p.2.2.6)
Rosva Industrial Park:
- Preparation of planning project and boundary-setting plan for Rosva Industrial Park
- Design and construction of facility: Stormwater drain system at the Northern and Eastern sites of Rosva Industrial Park, Kaluga Region. Phase 3
- Construction of utilities infrastructure for integrated development of the Northern site of Rosva Industrial Park, Kaluga Region
- Design and construction of 10kV cable line and 10kV Distribution Station at the Eastern site of Rosva Industrial Park
- Design and construction of facility: Stormwater drain system at the Northern site of Rosva Industrial Park, Kaluga
Kaluga-Yug Industrial Park:
- Preparation of planning project and boundary-setting plan for Kaluga-Yug Industrial Park
- Design adjustments for motor roads at Kaluga-Yug Industrial Park
- Design and construction of facility: Pedestrian paths at Kaluga-Yug Industrial Park
Sosensky Industrial Park:
- Construction of power supply system for Sosensky Industrial Park
- Access motor road to the territory of Sosensky Industrial Park in Sosensky town, Kozelsk District, Kaluga Region
Kaluga Special Economic Zone of industrial type. Lyudinovo site:
- Grid and facilities of free-flow stormwater drain system (III Phase)
- Motor roads of industrial enterprises with lighting (II Phase)
- Motor roads of industrial enterprises with lighting (I Phase)
- Service water, potable water, industrial water, fire water supply grids
- Grid and facilities of service and household sewage
- Low-voltage power grids
- Internal 10 and 110 kV power grids and facilities
- 110 kV power grids and facilities
- Power supply for Kronospan OOO
- 220 kV Distribution Station Voylovo
Kaluga Special Economic Zone of industrial type. Borovsk site:
- Grid and facilities of service and household sewage, I and II Phases
- Grid and facilities of free-flow stormwater drain system
- 110 kV power grids and facilities, I and II Phases
- 10 kV power grids and facilities
- Motor roads of industrial enterprises with lighting
- Fencing of territory
- Buildings and facilities of customs infrastructure
- External utilities infrastructure. Off-site access motor road
- 5MW cable line from Rusinovo Distribution Station
- Service water, potable water, industrial water, fire water supply grid and facilities
City of Kaluga Municipal Structure:
- Construction (rehabilitation) of water supply grids for connection of Globus Hypermarket, separately located commercial and household services capital facility
- Construction (rehabilitation) of water supply grids for connection of Sport Palace complex, 57, Lenin Street, Kaluga
- Construction (rehabilitation) of water disposal grids for connection of Sport Palace complex, 57, Lenin Street, Kaluga
- Construction (rehabilitation) of water supply grids for connection of Commercial Building
- Construction (rehabilitation) of water disposal grids for connection of City Market with season farmers’ market
- Construction (rehabilitation) of water supply grids for connection of Car Service and Dealer Center
Borovsk Municipal District, Kaluga Region:
- 220 kV ‘Sozvezdie’Substation, Dobrino
- Sewage treatment facilities, Ermolino, Borovsk District, Kaluga Region, extension of capacity up to 20, 000 m3/day for tie-in of SEZ Kaluga AO
- Water disposal grid, Ermolino, Borovsk District, Kaluga Region, for tie-in of SEZ Kaluga AO
- Rehabilitation of 110/35/10 kV Substation Vorsino. Replacement of Т-2 transformer, upgrade from 10 MW to 16 MW
- Rehabilitation of 110 kV Vega Substation. Replacement of Т-1 transformer, upgrade from 16 MW to 40 MW
- Rehabilitation of 110 kV Vega Substation. Replacement of Т-2 transformer, upgrade from 16 MW to 40 MW
Zhukovsky Municipal District, Kaluga Region:
- Rehabilitation of 110/35/10 kV Substation Protva. Replacement of Т-2 transformer, upgrade from 25 MW to 40 MW
Maloyaroslavets Municipal District, Kaluga Region:
- Utility connection of Maloyaroslavesky Solepromysl OOO to water supply grid of Maloyaroslavetsmezhraygas OAO
- Construction of facility: Power supply line to facility: Development of Vorobyevsky Site of NaCl Field, Maloyaroslavets District, Kaluga Region
- 500 kV Obninskaya Substation with tie-in points, near Tinyakov Settlement, Maloyaroslavets District
Spas-Demyansk Municipal District, Kaluga Region:
- Modernization of motor road Stayki-Alfimovo-Davydovo (access road to Stayki Cattle Breeding Farm) at section 0+000 km - 1+300 km in Spas-Demyansk District
Sukhinichi Municipal District, Kaluga Region:
- Construction of motor road Sukhinichi-Verkhovaya, facility of Mooloko Group OOO, Sukhinichi District
- Modernization of motor road Strelnya-Frolovo, facility of Byrlya S.P. Family Farm, Sukhinichi District, Kaluga Region
- Modernization of motor road Shlippovo-Ugra-Naumovo (access road to Naumovo Cattle Breeding Farm) at section 0+000 - 1+316 km, Sukhinichi District, Kaluga Region
Ulyanovsky Municipal District, Kaluga Region:
- Construction of motor road Pozdnyakovo-Kasyanovo-Losev, Ulyanovsky District, Kaluga Region